Client Name: Green Arch Developers
Problems Faced:
The project initially had only a single coat of paint, which was a rather darker shade. The nature and colour of the existing paint made the buildings appear aged, which reduced the overall aesthetics. This prompted the developers to reach out to Berger Paints India Limited for better colour options.
The primary challenge was to complete the entire painting process, across 15 towers, within a 2-month timeframe in the most cost-effective manner.
Solution Offered:
Berger Paints India Limited considered all the requirements and shortlisted the best colour combination for the repainting of all 15 towers. We provided 3 different teams of contractors with ample manpower to execute the painting process smoothly without any delays or hiccups.
Additionally, Berger Paints India Limited also ensured the constant availability of material, which meant there was no shortage in supply. We completed the project within the prescribed time frame and delivered 15 swanky-looking towers in January 2023.